Serving the region, protecting
our resource.

Jaycox Waterline Replacement 2019

Updated 12/3/2019

The Jaycox Waterline Replacement project is scheduled to begin Monday, January 6, 2020. This project will replace the waterline on Jaycox Road that runs from Walker Road to the Avon Lake/Avon border (the railroad tracks). The project is scheduled to begin January 6th and last through May.

The contractor for the project works 7:00 a.m. to 5:00 p.m., Monday – Thursday (work will occur on Friday if there is a weather day earlier in the week). The contractor will work from Walker Road towards the railroad tracks. The Avon Lake Police Department will be onsite to direct traffic around the contractor’s work area. Jaycox Road will be open to traffic, just reduced to one lane in the work area during working hours.

Avon Lake Regional Water mailed project notice letters to all Jaycox Road residents impacted by the project during the week of December 2nd.